January progress included completion of the concrete bridge deck for Phase I of the project from Ohio Street Beach to Ogden Slip, as well as the north and east access ramps.  Work continued on installation of the north and south stair structures and excavation began for installation of the final retaining wall and pavement near Ohio Street Beach.

Work in February will focus on installation of the retaining wall and pavement near Ohio Street Beach and completion of the stair structures.