The installation and painting of the bridge railing and enclosure systems continued in July, and preparation began for the installation of the segmental concrete block wall at Jane Addams Park. In addition, the bottom of the concrete bridge deck was given an architectural finish and the installation of electrical systems began at the east ramp.

 

In August, installation of railing, enclosure and electrical systems will continue along with  the segmental concrete block wall and permeable pavers at Jane Addams Park.  Landscaping and sidewalks will also be added throughout the project.