Navy Pier Flyover

Enhancing Chicago's Lakefront Trail

March Update

This month, construction crews are installing drilled micropile to support the concrete piers next to the Ogden Slip. Concrete placements to finish the south abutment near the Chicago River, as well as construction of the piers adjacent to the Ogden Slip, are anticipated toward the end of March.

Intermittent off-peak closures of the right lane on Northbound Lower Lake Shore Drive may be required as materials and equipment are delivered to the site. All closures are being coordinated with Navy Pier to limit public impact.